Appearance of the President of the Government of Spain before the plenary session of Congress to report on the latest accidents and the current situation of the railway service
Pedro Sánchez · Prime Minister of Spain
- Context
- Sánchez addressed the Spanish Congress plenary in February 2026 to report on a deadly train derailment and collision near Adamuz on 18 January 2026.
- Main themes
- Railway accident investigation, train derailment and collision, emergency response coordination, victim assistance, infrastructure safety, accountability and transparency, inter-institutional cooperation, CIAF preliminary findings, rail track maintenance failure
- Duration
- ~32 min
- Words
- 3,851
- Sentences
- 147
- Readability
- 49
- Grade
- 12.6
- Syntax
- 3.21
- Vocabulary
- 2.22
The broad sphere of national life a sentence belongs to. Every sentence has an Arena, so it is the denominator the other indices are read against.
Other147 sentences in 42 paragraphs
Ladies and gentlemen, as you know, this tragedy began on Sunday 18 January at 7.43 p.m., when the last three carriages of Iryo train number 6189 derailed. This train was travelling on the Malaga-Madrid route, at Adamuz, where this tragedy occurred. These three carriages invaded the adjacent track, and unfortunately another train, Renfe Alvia number 2384, was passing at that moment, causing a terrible collision between the two trains. Moments later, the voltage on the track dropped, which brought the traffic on that section to a standstill and set off the first alarms.
Two minutes later, at 7.45 p.m., the driver of the Iryo contacted the Adif Control Centre to explain that he had suffered a derailment, although he himself was not yet aware that there had been a collision with another train. A minute later, the Alvia controller informed Renfe of a heavy impact, describing what had happened as a major accident.
At 7.50 p.m., the Adif Protection and Security Centre activated the emergency device. At 7. 55 p.m., the first injured people on both trains were already known and five minutes later the first Guardia Civil patrol arrived at the scene of the accident, followed by the first medical services.
By then, the Adif Crisis Committee had already been set up. The Plan for assistance to victims and family members of the public company Renfe had been activated, and the creation of care centres in Cordoba, Huelva and Madrid was also set in motion.
As Minister Puente has already explained in different appearances, from 8:00 a.m. onwards, a wide-ranging response system was deployed, both in the area of the incident and also in the railway stations and other facilities set up.
Some 500 deployed and specialised personnel and resources from the Armed Forces, the Civil Guard, the National Police, the General Directorate of Traffic and also the State Civil Protection System took part in this operation. Around 150 emergency professionals, psychologists, Renfe medical staff, 50 ADIF workers from the ADIF care services for affected people and their families, and numerous firefighters, local police and medical staff from different public institutions joined the team. In short, what I would like to tell you, ladies and gentlemen, is that in a matter of minutes a wide-ranging State-wide system was activated.
This was done in close coordination and cooperation between different administrations. And I believe that this collaboration, this coordination, allowed for a rapid and orderly response to the tragedy, and I sincerely believe that it helped to save lives.
That is why I would also like, in this introduction, to express my gratitude to all the public institutions, the State law enforcement forces and agencies, the members of the Civil Protection System and all the other professionals of the General State Administration. Gratitude which, of course, I extend to the Junta de Andalucía, the Diputación de Córdoba, the Adamuz Town Council and all the neighbours in the area. Because their professionalism, their dedication, their generosity, their solidarity, their empathy, in short, their humanity, I believe that they will remain fixed in the collective memory as an indelible symbol of how great our society, our country, is, above all and especially when tragedies of this kind occur.
Ladies and gentlemen, as soon as the victims had been assisted, the competent authorities began to investigate the incident. On the evening of the 18th, a team of investigators from the Independent Commission of Inquiry into Railway Accidents (CIAF), the Commission as you know that is responsible for investigating railway accidents, travelled to the site. They worked together with the Guardia Civil to preserve the evidence and carry out initial investigations. Samples were taken, photos were taken, measurements were taken, several fragments of metres of track and also several tonnes of rolling stock were transferred to the city's laboratories.
Just five days after the tragedy, a time that I believe is a record for this type of accident, the CIAF published a first preliminary report pointing to a possible breakage of the right rail as the cause of this tragedy. A breakage that would have occurred at a weld made a few months earlier during track renewal works. This hypothesis is supported by the notches detected on the right wheels of Iryo carriages two, three, four and five, and on three other trains that had previously run on that section, specifically: one Renfe train at 7.09 p.m.; two Iryo trains, one at 5.21 p.m. and the other at 7.01 p.m.
CIAF technicians are currently examining the remains to determine the causes of the breakage, while additional evidence is still being gathered, because this is indeed a preliminary study and is therefore not conclusive.
What I can say, of course, to the families of the victims, to the injured, to Spanish society as a whole, is that as soon as we have these conclusive results, obviously, as we have done from the beginning, we will share them with the rest of the public administrations and, of course, also with public opinion in a totally transparent and independent manner, as we have been doing, with appearances in the Upper and Lower Houses, with press conferences with no time limit, such as those given by the Ministry of Transport, and specifically by its head, Óscar Puente.
And once we know exactly what went wrong, we will put in place the necessary measures to ensure that this kind of tragedy does not happen again. In the meantime, ladies and gentlemen, what we can do is analyse the context, inform the public and facilitate the work of the technicians. But what we cannot do is speculate. We cannot misinform and we cannot use this tragedy to stir up tension.
First of all, I think it is necessary to talk about the state of the track and also about the inspections carried out before the accident. As you know, the incident occurred on infrastructure that was completely renovated last year, in 2025, with a specific investment of 780 million euros.
In recent weeks, attempts have been made to generate confusion around this concept, the concept of complete renovation of the track, which, as Minister Puente has explained on many occasions, does not imply the complete replacement of all the elements, as might be thought, for example, outside the technical sphere - and I believe that the analogy may also be useful to those people who are perhaps listening or following this hearing, if we take it to a much more colloquial term - in the same way that it does not mean completely renovating a house implies demolishing it and building it from scratch.
According to the European Union Agency for Railways - and I think it is also important to make this reference - according to the European Union Agency for Railways, a track renewal is: the planned process of replacing those components that have reached the end of their useful life, with the objective of maintaining or restoring the infrastructure in a safe and reliable condition for the running of trains. It is therefore, ladies and gentlemen, absolutely standard procedure, fully standardised in the railway sector, and also in line with national, European and international technical and safety standards. The renewal, therefore, that concerns us, was completed in June 2025, and affected both the infrastructure and, therefore, we are talking about the platform, the structures, the tunnels, as well as the track itself, that is, the turnouts, the sleepers, the ballast and also the rails.
In the specific section, in addition to the accident, three contracts were executed, one for the integral improvement of the infrastructure, another for the renovation of the Adamuz turnouts and a third for the implementation of the European Rail Traffic Management System, with a joint investment of 180 million euros.
I would therefore like to make one thing very clear. This renewal was carried out in accordance with the highest quality standards by leading companies worldwide and passed all the technical inspections required by current regulations. And I would also like to say, ladies and gentlemen, for your peace of mind and that of Spanish society as a whole, what these inspections are. Specifically, the 114 welds on the section were first inspected by visual checks, geometric tests and also ultrasonic tests. Secondly, geometric checks of the track were carried out on two occasions, specifically on 8 September and 13 October 2025, as Minister Puente has already explained, to verify that the alignment, level and gauge remained within the safety margins. Thirdly, five dynamic auscultations were carried out between June and November 2025 to evaluate the behaviour of the track under real traffic conditions.
Finally, two more aspects that I think it is important to underline: An ultrasonic monitoring was carried out on 10 September 2025 and a technical inspection of the turnouts on 7 January 2026.
Finally, 13 track tamping operations were carried out, the last of them, ladies and gentlemen, on 6 November 2025, as part of ordinary maintenance to ensure the stability of the infrastructure. The result of all this, ladies and gentlemen, as I said earlier, is that only four incidents were detected on this stretch. None of them, as Minister Puente has said on many occasions whenever he has had the opportunity to appear, none of them were related to the state of the track and all of them were resolved according to standard procedure. What does this mean, ladies and gentlemen? The track strictly complied with all the maintenance and control protocols established by the Spanish and European authorities.
It is likely that one of the lessons we will all learn from this terrible tragedy is that these protocols are clearly not infallible because of what we have suffered, that the quality standards and control tests that are part of them need to be extended and also improved. And if this is the case, you can be sure that the Government of Spain will be the first to reinforce it, following the indications given by the experts to prevent a similar episode from happening again in our country. But having said that, ladies and gentlemen, I think it is also important, just as important, not to misinform society or generate fear by saying that our railway system is decadent or unsafe, because that is simply not true. Look, the Spanish railway system is not perfect. That goes without saying. It has significant shortcomings and these will also emerge in the course of this debate, especially in some territories. It suffers from incidents. There is work to be done, no doubt, but there is also much room for improvement.
We can all agree on this, with varying degrees of intensity, more or less, but I think it is also important to share with the citizens, in the heat of this debate, three fundamental things. The first is that despite the problems with the railway system in our country, our system is one of the best in the world. I repeat, it is one of the best in the world. And I am not saying this as president of the Government of Spain. This is stated, for example, in the ninth report of the European Commission, the so-called Prime Report of the Community infrastructure operators, and also in various studies by the European Federation for Transport and Environment. Spain, ladies and gentlemen, to give us an idea, has a rail network of 15,700 kilometres, I repeat, 15,700 kilometres. In other words, it is the fifth largest on the European continent. Of this, 4,500 km is high-speed railway, making us the second country in the world only behind China in terms of kilometres of high-speed rail. Therefore, we are behind China, as I said before, but we are ahead of large economies, large countries, such as the United States, Japan or Germany. As recently as 2025, our system was the most reliable in the European Union and the fifth most punctual. And it was, moreover, and I think it is also important to share this with the citizens who are following this hearing, with one of the most competitive prices. Every week in Spain, ladies and gentlemen, more than 12 million people use the train. I repeat the figure. Every week, 12 million people use the train. They do so safely, with good frequencies and at a price infinitely lower than their European neighbours. To give us an idea and to compare the reality in Spain and the rest of Europe, to travel the 534 kilometres from London to Edinburgh costs more than 100 euros and four hours, more than 100 euros and four hours. The journey between Madrid and Barcelona, which is 87 kilometres longer, is, however, much cheaper because it is half the price and half the time. The same comparison could be made, for example, with the Berlin-Prague route or also with Rome and Venice. I therefore insist on something very important, ladies and gentlemen, and that is that this system is not perfect.
Unfortunately we have suffered a terrible tragedy, but it is safe. This is the second thing I want citizens to know, to be clear about. You see, if we put all our track in a straight line, all 17,000 kilometres of straight line, it would cover the distance between the coasts of the North Pole and the South Pole. This is the reality. In such an extensive system, ladies and gentlemen, in such an extensive system, there are obviously incidents every day and this is inevitable. There are animals that cross the tracks, there are trees that fall, there are parts that break down, there are train drivers who fall ill, there are problems that arise from the climatic emergency, which is affecting our infrastructure increasingly more often, as we have unfortunately seen in recent weeks, as a result of the successive storms that have hit the Iberian Peninsula. That is why, ladies and gentlemen, there are temporary speed reductions, there are stoppages to act on the catenary, there are specific detours to update the infrastructure. All this, ladies and gentlemen, is a nuisance, no doubt, but they are not anomalies, they are not dysfunctions.
On the contrary, they are part of the normal functioning of a complex and permanently monitored system. In short, what I mean by this, ladies and gentlemen, is that it is proof that the system detects, acts and corrects. That is why, when accidents like the one in Adamuz occur, what we have to do is investigate, learn from them and, therefore, also take measures and act accordingly so that what caused this tragedy does not happen again and so that the system is better every day. The Government is committed to doing so, ladies and gentlemen, it is committed to Spain having one of the best railway systems in the world. And it is important to note that this commitment does not start from the accident of the tragedy, not at all, it has been going on for many years, and this is also something I would like to share with the citizens.
And this is the third message I would also like to convey to you. Look, as a consequence of the tragedy - and unfortunately it is now recurrent every time there is a crisis - many hoaxes have been launched over the last month. One of the most recurrent is that the accident occurred because the government no longer invests in maintenance and only invests in transport vouchers. But let me be clear on this issue, because this is a colossal lie, it is a big lie, and I believe that the data will corroborate the position of the Government of Spain.
Since 2018, we have almost tripled investment in rail infrastructure. Moving (I'll talk about kilometres later) from 1.7 billion euros to around 5 billion euros in 2025. Therefore, in 2018 the investment was 1.7 billion euros and in 2025 it was 5 billion euros. Over the bulk of this period, investment in railway infrastructure in Spain has grown at a higher rate and I believe that it is also important - because it has been mentioned in some of the media - in real terms, that is to say, discounting inflation. And we have done so at a higher rate than benchmark countries such as, for example, France or Germany. And in the case of high speed, if we specify and focus on high speed, this investment has increased by almost 75%. That's 75%.
Something similar has happened with the purchase of railway equipment, which is something that has always been recurrent in the presence of published opinion or public opinion on the state of railway equipment. Well, investment in the acquisition of new trains and new equipment has increased tenfold, going from an annual average of 150 million euros between 2011 and 2017 - an annual average, I repeat, of 150 million euros - to more than 1.5 billion euros under the current government. What has happened to maintenance expenditure? The same applies. Since 2018, this expenditure on rail track maintenance has increased by 54% and maintenance per kilometre of track (which is what some of you have been saying) has gone from €46,000 under Mariano Rajoy's administration to more than €71,000 and, therefore, an increase of more than 50%, both in absolute terms and also in kilometres travelled.
Even if we take into account inflation, the increase in the cost of materials which, of course, has occurred over all these years, we can see that the Government of Spain spends 26% more on maintaining the rail network than the previous People's Party administration did. In fact, our expenditure on renewal and maintenance per kilometre of track is also above the European average and I think this is important to note. What do I mean by all this, ladies and gentlemen? Let us not deceive the public. Between 2012 and 2018, investment in rail infrastructure was halved, and today Spain invests almost three times as much, at levels comparable to those of the most advanced countries in the European Union, to which I referred earlier.
Ladies and gentlemen, all this investment effort goes far beyond the spreadsheet and is yielding tangible results. Despite this tragedy that we have experienced in Adamuz, and also in the Catalan town of Gelida, since I have had the honour of governing this country, the average number of serious and significant railway accidents in Spain has fallen 11% compared to the period 2012-2018, despite the fact that the number of passengers has increased around 15%. So, I repeat, rail accidents have been reduced by an average of 11%, while the number of passengers has increased 15% since we have been in government. In other words, there is much more rail traffic and there are fewer rail accidents.
Of course, in the light of recent events, it is legitimate to ask a question that I think we can all ask ourselves, and I am the first to do so, and that is whether the current level of investment is sufficient. And I believe that this is a necessary and timely debate that we must hold in this Chamber because citizens are also asking us to do so. In this respect, ladies and gentlemen, we are going to act.
At the moment, we have just concluded an important agreement with the sector that will serve to reinforce safety and also, we hope, the satisfaction of passengers and workers in the railway system. In particular, we have agreed to increase investment in maintenance by 1.8 billion euros. We have also agreed to reinforce the Adif and Renfe workforces with 3,600 new employees in driving, stations, maintenance and operations. We are going to guarantee replacement rates of no less than 115% in the General State Budget and we are going to strengthen the State Railway Safety Agency with 50 additional professionals so that it can better carry out its inspection tasks on the network. We are going to create a Committee for harmonisation and coordination in the shared management of safety, a Group for monitoring temporary speed restrictions and also infrastructure, and another Group for meteorological alerts, as a consequence of the increasingly serious climatic reality we are facing.
These measures, as you know, have been agreed with the major trade unions in the sector. And if, when their investigations are concluded, the CIAF experts tell us that we need to do more, we will do so, ladies and gentlemen. The public, including you, can be sure of that.
We will do so to honour the victims of this tragedy. And to honour the injured and the families of the victims of this tragedy. We will also do so, ladies and gentlemen, because this Government is a Government that believes in public transport. Because we also know that the train unites territories, mitigates climate change and also reduces social barriers. And also because, ladies and gentlemen, we want Spain to have and to continue to have one of the best railway systems in the world.
And in the meantime, as we move towards that future, we will continue to honour those who died in the Adamuz accident, as well as the train driver from Gelida. We will continue to support their families and all the people who were travelling on Iryo 6189 and Alvia 2384.
What have we done in this respect, ladies and gentlemen? Well, as you know, on 27 January, the Council of Ministers approved a Royal Decree Law to advance up to 20 million euros in compensation and accident insurance, which also establishes and guarantees the labour protection of workers and the workers affected, avoiding any harm resulting from the accident. Also, as you know, we have set up physical and psychological support units for victims, and Comprehensive Care Offices to facilitate the management of aid, together with preferential channels in the Social Security system.
Just today, a Royal Decree that we approved yesterday also came into force to protect travellers, preventing mobility companies from increasing their fares, as they are doing, in emergency situations.
Finally, ladies and gentlemen, I would, of course, like to address the victims and their families.
The Government will be at their side today, tomorrow and for as long as it takes. We will accompany them and help them in any way we can.
Also in their pain, which is a pain we share.
Let there be no doubt that we will implement all recommendations that may result from the CIAF investigation to make our tracks even safer. We will reinforce, as we are doing, the financial, human and technical resources dedicated to the railways with the aim of always improving their efficiency and safety and giving users what they deserve and demand, which is quality, speed and punctuality in the management of this service.
We, ladies and gentlemen, are going to support trains to bring people together, to integrate our territories and to ensure that Spain continues to be a world benchmark in sustainable mobility.
That is all, thank you very much.