The President launched the first phase of the energy bridge to Crimea.

Russia Vladimir Putin · President of Russia

2 December 2015 · Launch of the first phase of the energy bridge to Crimea

Context
Putin launched the first phase of the energy bridge connecting Crimea to Russia's unified energy grid via the Kerch Strait on December 2, 2015.
Main themes
Crimea energy integration, energy bridge construction, electricity supply to Crimea, high-voltage power lines, underwater cable lines, Kerch Strait crossing, thermal power plant development, energy system unification, Russian infrastructure investment, energy independence from Ukraine
Duration
~14 min
49th percentile
Words
1,681
49th percentile
Sentences
70
46th percentile
Readability
50
63rd percentile
Grade
11.9
44th percentile
Syntax
3.15
66th percentile
Vocabulary
2.18
45th percentile

Translated from Russian

This is an interview, press conference or exchange with other speakers. It is split into sentences and counted in the corpus, but its sentences are not tagged on the twelve indices.

70 sentences in 37 paragraphs

Dear colleagues! Today we have an important event: we are starting work on integrating the Crimean Peninsula into the unified energy system of Russia.

The people who are present here – both behind me and in front of me – your teams and you personally have done a tremendous amount of work related to the reliable supply of electricity to Crimea. Over a hundred kilometers of high-voltage power lines have been built, and today we are connecting the first circuit.

I would like to remind you that Crimea previously received 800 megawatts from Ukraine. The four branches, four circuits that are to be built by December 20, will also transmit around 800, just over 800 megawatts. After that, it will be necessary to add generation as soon as possible.

In 2017, we will supply gas here from the Caucasus, and by the end of 2017, a thermal power plant should be built that will provide another 470 megawatts. In 2018, there will be two more units and another 470 megawatts, meaning Crimea will receive generation that will not only supply all existing consumers but will also have significant resources for development – for the development of the household sector, the recreational sector, and all promising areas of economic development.

A lot of work has indeed been done. I want to thank all of you because it was planned that the first circuit would be launched by December 20. Now we are launching the first circuit. Of course, there is a lot of new equipment being used in this project, so it will probably need further adjustments. We must also warn consumers – citizens, residents of Crimea – that there may still be some disruptions. But overall, the first circuit should operate stably – that is 200 megawatts.

I hope that, as agreed, or perhaps even earlier – not by December 20, but a little earlier, at least by the 15th – the second circuit will be launched, and that will be 400 megawatts.

I ask the Minister of Energy of Russia, Alexander Valentinovich Novak, to report on how the work is progressing and what should happen in the near future in terms of consumption.

A. Novak: Dear Vladimir Vladimirovich! By your order in April 2014, a power supply scheme for the Crimean Federal District was developed, and this scheme, as you just mentioned, involves the construction of two power plants: one in Sevastopol, with a capacity of 470 megawatts, and the second in Simferopol, also with a capacity of 470 megawatts; a total of 940 megawatts, with deadlines set for 2017 and 2018.

The second direction is to connect the Crimean energy system with the Kuban energy system, with the unified energy system of Russia through the construction of four underwater cable lines, each of which will be 220 kilovolts and have a capacity of 200 megawatts; this totals 800 megawatts, across the bottom of the Kerch Strait.

This includes the construction of two new substations: the "Taman" substation with a capacity of 500 kilovolts with the first phase at 220 kilovolts, and the "Kafa" substation – a completely new station. And more than 500 kilometers of high-voltage power lines: 220 kilovolts and above. As you just mentioned, indeed our deadlines were quite tight, but they were set for December – the first 400 megawatts, and for May 2016 – the second 400 megawatts.

Given the situation that has developed since the end of November with zero flows from the Ukrainian system, a decision was made to take all necessary measures to accelerate the construction of the first circuit – 200 megawatts – and the 400 that were planned to be introduced in December of this year. And thanks to the builders who are here, our energy workers have completed this work, and today we are ready to launch the first launch complex and connect the Kuban energy system with the Crimean energy system, for the first time in history connecting the Crimean energy system to the unified energy system of Russia and transmitting a capacity of 200 megawatts.

For this, the work on the construction of the "Taman" substation, the construction of the first of the four circuits – laying the cable and putting it into operation – was completed in the shortest possible time. At the Kamysh-Burun station, cells were reconstructed, and inserts were made to the existing line from Slavyanskaya to Vyshesteblievskaya, which will allow it to connect to the unified energy system.

This is the first stage. By the end of December – by the 20th, or perhaps, as you set the task, we will manage to do it earlier, we will strive for that – we will supply another 200 megawatts, put the "Kafa" substation into operation, as well as the second line – the underwater cable transition (200 megawatts) and the power line from Kamysh-Burun to "Kafa" with inserts from the existing Feodosia substation. This will provide another 200 megawatts.

Vladimir Vladimirovich, we have already checked the readiness of our energy system today, we contacted the "Taman" substation, the "Kamysh-Burun" substation, with the transition points in Crimea and in Taman, where our cable comes ashore, and we are now ready, at your command, to instruct the dispatcher to connect the consumers.

Wait a moment, let’s figure out how this new electricity will be distributed on the peninsula.

A. Novak: Allow me to report, Vladimir Vladimirovich: from the moment we start connecting consumers, literally today we will be able to ensure electricity flows of about 100 megawatts from the first 200 megawatts that this underwater cable circuit allows. I believe we will gather the second 100 megawatts within the next day.

There are currently some operational features of the energy system. In order to complete the commissioning work and ensure reliable power supply, in the first 24 hours there will be operation of a dedicated energy system, and primarily consumers located in the eastern part of Crimea will receive electricity: this includes Kerch, Feodosia, and about 180 settlements with a total consumption capacity of about 120 megawatts.

At the same time, subsequently, as we reach the capacity of 200 megawatts, we will need to transmit additional electricity to the entire Crimean energy system within the next few days, including to areas located in the central, northern, and southern parts. In this regard, we need to determine in the coming days how to distribute these 200 megawatts among consumers, so that it is fair in terms of power supply and electricity delivery to consumers.

Let’s ask the head of Crimea. Sergey Valeryevich, how is it best to do this – to concentrate it in one area, two areas, three, or distribute it evenly across all of Crimea?

S. Aksyonov: Vladimir Vladimirovich, I ask for your permission to distribute this resource evenly across all municipal entities of the Republic of Crimea; this will be fair: people are indeed all in the same situation. They send you personally words of immense gratitude, respect, and love; the people of Crimea appreciate you, believe in you, so they knew that you would not leave us without help.

I always say: "When there is such a leader, such a head – know that we will be supported." They believe and are proud of their country – Russia. Therefore, there is this proposal, Vladimir Vladimirovich, if you support it – to distribute this resource evenly.

Evenly, but we need to get the remaining 200 megawatts as quickly as possible and add them. (Addressing A. Novak.) As you said, this will be within a day. I remind you again that by the 15th-20th – plus another 200 [megawatts].

A. Novak: Plus another 200, it will total 400 [megawatts].

And in May – I would ask you to do this as quickly as possible too, before the start or even in preparation for the summer season – so that there will be another 400, and thus we would completely replace the supply of electricity from Ukraine, entirely, even a little more than we had before. And of course, it is necessary to synchronize this with the gas workers, with the builders of the thermal power plant, so that in 2017 we can already provide additional local generation for Crimea.

A. Novak: Understood, Vladimir Vladimirovich.

In accordance with your decision, as we reach the load of 200 megawatts within a day, all this electricity will be evenly distributed among consumers in the territory of the Crimean Federal District.

Let’s get to work.

The launch of the first phase of the energy bridge to Crimea.

I would like to emphasize once again that a lot of new equipment is involved, and if there are disruptions, do not panic, but calmly and rhythmically restore order, bringing everything to a normative state, but it is preferable to do this quickly – so that people feel the changes for the better.

And of course, I want to thank all the energy workers, builders for what has been done, the leadership of Crimea and Sevastopol – for their energetic involvement, working directly with the people. The work is still far from complete; there are many stages of this work ahead. I am confident that everything will be done within the timeframe we discussed, and at a high level of quality.

Congratulations to you all, thank you.

<…>

Sergey Valeryevich [Aksyonov], please thank the people of Crimea once again for their restraint, for believing in you, in all of us.

S. Aksyonov: And they are ready to endure. We even receive calls saying, "We don’t need anything from them for free – from our former ones."

We have never taken anything for free from anyone. But this will be a reliable own generation system, connected to the main energy system of Russia, and plus our own in 2017-2018 will be more than what we received from Ukraine today. Therefore, we will ensure the possibility for the development of Crimea's economy for a sufficiently serious, at least medium-term perspective.

S. Aksyonov: Thank you very much, Vladimir Vladimirovich.

Thanks to the people of Crimea.